Annex 1
3. INSTITUTION
3.1. Detail of existing Community Based Organisation in the community (CB0/FUG/SHG/Local Clubs /farmers
group/cooperatives)
SN Name of CBO
Date of CBO
Formed
Registered
No CBO members
List of major
activities
initiated by CBO
name of support
organisation
Remarks
3.2. List the potential vendors/supplier in the project area (if any)
SN Name of the supplier/vendor
Location
Major item
Distance form project site
3.3. List down the potential manufacturer/fabricators
SN Name of the supplier/vendor
Location
Major work /scale
Distance form project site
3.4. Local DDC/VDC support/commitment
Do the DDC and the project VDC agree with the selected site? What is their commitment for the project?
Interview the authorised staff or members of DDC/vdc
SN Name
Address
Function
Remarks
In addition, get a letter of confirmation regarding the site selection from VDC secretary or Chairperson.
61